MECCA is building its future Islamic center on a 4.7-acre site

located at 16 W 560 91st Street in Willowbrook, Illinois.

See Pictures 

MECCA Future Islamic Center at a Glance

MECCA is building its future Islamic center on a 4.7-acre site, located at 16W560 91st Street in Willowbrook, Illinois. The overall project provides the followings facilities:

 

ü  Prayer halls, a library, classrooms, meeting rooms, and an imam office.

ü  A main foyer will connect major elements of the building and provide the master entrance to the Mosque.

ü  A Gym to be used by the youth and others.

ü  A multipurpose hall, administrative offices, and a conference room.

ü  Plenty of green space and parking around the facilities

 

Construction Progress Report

Work Completed So Far:

ü  Site demolition and tree removal

ü  Site grading and earth movement

ü  Storm trap system construction

ü  Site utility installation (water, storm, sewer)

ü  Value engineering study

ü  Placement of the retaining wall on west side of property

ü  Final site grading

ü  Complete 30% of Masjid Foundation

Work To Be Completed By End of October, 2014:

Item

Amount of Contract

Duration Days

Task Start Date

Task Finish Date

 

 

 

 

 

Site Final Grading

$120,000

210

4/1/2014

10/31/2014

Reinforced Concrete

$596,000

50

6/1/2014

7/20/2014

Precast Concrete Walls

$775,000

30

8/5/2014

9/5/2014

Thin Brick

$183,000

30

8/5/2014

9/5/2014

Hollow Core Planks

$160,000

30

8/5/2014

9/5/2014

Precast Concrete Columns

$15,000

30

8/5/2014

9/5/2014

Structural Steel

$605,000

15

7/20/2014

8/5/2014

Roofing & Sheet metal

$150,000

15

9/5/2014

9/20/2014

Sealant/ Caulking/ Waterproofing/ Damp proofing

$60,000

100

7/20/2014

10/31/2014

Skylights

$50,000

55

9/5/2014

10/31/2014

Glass & Glazing

$300,000

55

9/5/2014

10/31/2014

 

 

 

 

 

Totals

$3,014,000

 

 

 

 

 

Construction Project Costs & Payable by October, 2014:

Total Cost of Project: $8,492,000

 Total Amount Spent So Far: $2,850,000

o   Engineering & legal: $500,000

o   Permits: $250,000

o   Construction: $2,100,000

 

 

Accounts Payable by October, 2014: $3,014,000

 

How to Receive an Everlasting Reward?

Sponsor the cost of any part of MECCA Center (please see cost breakdown) or be a Founder by committing to give a minimum of $1000 per month (or $12,000 per year) for 2 years. Your name will be listed on a wall Founders Plaque insha’Allah.

 

 

 

To Donate:

  • By Check:  Mail your check to: MECCA Center at 720 E Plainfield Rd, Willowbrook, IL 60527.

  •   All donations are tax deductible and MECCA will send a receipt for your records.